Home » 2017 » Fish out of GMW’s water plans

Fish out of GMW’s water plans

A CASTLE Donnington irrigator has criticised Goulburn-Murray Water’s (GMW) plans to lower the Little Murray River, however the water company has strongly denied his claims.

Last week, GMW announced it is moving ahead with plans to lower the Little Murray River by two metres as part of its $27 million Swan Hill Modernisation Project to deliver more reliable and efficient irrigation to landholders in the Swan Hill Irrigation Region.

The works, which have currently been in the planning phase for almost two years, are set to commence between May 15 and August 15 next year and aim to provide fish passages at the Lower Murray Weir and Fishpoint Weir.

However, Castle Donnington irrigator Ron Sonogan, who sat on the Little Murray River stakeholder committee which GMW assembled to consult with, said irrigators downstream of the weir weren’t happy with the situation.

“At least half the things we asked for never got addressed, they just got whitewashed in a terrible, terrible consultative process,” Mr Sonogan said.

According to Mr Sonogan, water costs would have to be raised as a result of reducing water from the gravity supply.

Despite this, Mr Sonogan claimed GMW has only made agreements with irrigators upstream of the river to move to a diverter’s license and install individual pumps, while irrigators downstream have not been contacted.

He was also unconvinced of GMW’s 40-year modelling which showed the Little Murray Weir was in poor condition and likely soon to fail altogether, arguing local stakeholders had presented GMW with a proposal to save its health over the next century.

“The process that’s going to cause it to fail could actually be treated by a surface treatment of the concrete — it may only cost $1 million. They would not address that — all they wanted to do was do away with the weir,” he said.

GMW Connections Project manager of environment and water savings Ross Plunkett said the costs of the project would fall under the $27 million for the modernisation project, and GMW had held an “extensive consultation process” which concluded in 2012 and was followed up by regular updates at council meetings and community groups.

“Once works are complete, the maintenance and ongoing operational costs will be less than the existing costs. There will be no additional material cost to customers for these works,” Mr Plunkett said.

“Instead of replacing the weir, the planned works include the lowering of the weir, which expert structural engineers engaged by GMW have found will address the ongoing structural and operational concerns. 

“The works include removing the piers and the lowering of the weir, which is expected to extend the life of the structure to 25 to 30 years.”

Digital Editions


  • Telstra upgrades improve connectivity

    Telstra upgrades improve connectivity

    TELSTRA is in the process of upgrading its mobile base station that services Balranald to bring a better 4G/5G user experience. Telstra said the upgrades…

More News

  • Drawing cultural connections

    Drawing cultural connections

    Sora Shim grew up in Seoul, South Korea, in a bustling household with five siblings. By age six, her family had moved 12 times, shaping her sense of responsibility and…

  • Raiders rout Roodogs

    Raiders rout Roodogs

    Barham-Koondrook have stormed their way into this year’s SHDCA A grade grand final after a comprehensive eight-wicket win over a disappointing Ultima-TUF on Saturday. In a ruthless display of skill…

  • Ley officially resigns

    Ley officially resigns

    SUSSAN Ley has formally quit Parliament, two weeks after being ousted from the Liberal Party’s top job. Her resignation as the member for Farrer will trigger a by-election in her…

  • Breast screening visit

    Breast screening visit

    WOMEN over 40 can book in for their free regular breast screen at the mobile van in Balranald between Saturday 11 April and Saturday 18 April. BreastScreen NSW manager Deon…

  • Record rainfall recorded

    Record rainfall recorded

    AN unseasonal downpour over the Mallee marked the transition from summer to autumn this weekend, as the tropical low and trough that caused flash flooding in parts of South Australia…

  • Rams make history

    Rams make history

    MURRAY Downs have claimed victory their very first Northern Valley premiership with a nail-biting finish that went down to the very last end. The final score was 52 shots to…

  • Questions over AI in basin review

    Questions over AI in basin review

    THE Murray Darling Basin Authority has confirmed that generative AI is not being used in the processes to assess submissions to the current Murray-Caring Basin Plan review. Consultations for the…

  • Mayors briefed on basin plan

    Mayors briefed on basin plan

    NORTHERN Victoria’s council chiefs have fired a warning shot over the future of the Murray-Darling Basin Plan, declaring their communities cannot afford another hit. The Murray River Group of Councils…

  • Tourism program sparks fresh ideas

    Tourism program sparks fresh ideas

    MORE than 50 tourism operators from across the Murray and Riverina regions gathered in Sunraysia recently to learn, connect, and explore ways to enhance or expand tourism offerings in the…

  • Landmark launch for tourism

    Landmark launch for tourism

    THE long-awaited revival of the heart of Swan Hill’s tourism and culture precinct came to fruition this week as community and stakeholders joined together for its official launch. Swan Hill…