Home » Farming and Environment » Plibersek seeks report on water recovery deadline

Plibersek seeks report on water recovery deadline

THE $13 billion Murray-Darling Basin Plan is “off track” and needs a “course correction”, according to federal Water Minister Tanya Plibersek.

Ms Plibersek has written to Murray-Darling Basin Authority chair Sir Angus Houston seeking advice on how likely it would be that the basin plan’s 2075-gigalitre water recovery targets would be achieved by the legislated June 2024 deadline.

Despite 98 per cent of the overall water recovery target already being met, there were parts of the plan, including NSW’s water resource plans, the sustainable diversion limit adjustment mechanism (SDLAM) projects, and the 450GL promised to South Australia that are well behind schedule.

“The plan is too far behind and likely requires significant change to make substantial progress,” Ms Plibersek said in the letter.

“A year from the deadline, this report will give us an honest assessment of the legacy we have received, including whether the plan can be delivered on time.”

One option for change could include extending the plan’s water recovery deadline to allow more time to complete the work.

“That option has to be on the table,” Ms Plibersek told the ABC.

Ms Plibersek expects to receive the requested report from the MDBA on July 24.

NSW and Victoria have both previously requested more time to complete SDLAM projects in their states.

After meeting of basin state ministers in October, Ms Plibersek said the Federal Government was committed to delivering the plan “but flexible about how we get there”.

The news the government was considering extending the basin plan’s deadline was welcomed by opposition water spokesperson Perin Davey, “if not 18 months late”.

“More recently, through the minister’s own consultation on how to finalise the basin plan, there have been many ideas submitted, but none that can be delivered within 12 months, so it is necessary to extend the deadlines,” Senator Davey said.

“Ideally, I would have liked the deadlines to have been extended prior to the last election, when the NSW and Victorian governments first asked, but we were dealing with a hostile Senate and Labor would not negotiate.

“Now the minister has realised there are a magnitude of reasons why the basin plan is behind schedule, not all within Federal Government control, I hope she is more open to having constructive discussions about how to enable the basin plan to be finalised to deliver the environmental objectives.”

Senator Davey rejected claims the basin plan was behind schedule because the Liberals and Nationals “sabotaged” its delivery, saying much of the implementation of the plan was dependent on states and out of Federal Government control.

“At the end of the day, the basin plan must be about environmental outcomes, not arbitrary numbers on a page,” she said.

“If the government wants to talk about how to deliver the basin plan with new ideas and new concepts that will improve our environmental resilience, my door is always open.

“I will not, however, consider plans to prioritise or allow increased buybacks that hurt basin communities and have flow-on impacts that will cost every Australian in the long run,” Senator Davey said.

South Australian Greens Senator Sarah Hanson-Young said action was needed now on rivers, not delays.

“A delay on the 450GL is a broken election promise to every South Australian and risks breaking our Murray River,” she said.

“This water must be delivered before the next election … South Australians are sick of excuses.

“Buybacks must be used now to secure the promised water, not a concocted delay designed to hide a broken election promise. That means standing up to the big irrigators in the upstream states.”

The National Irrigators’ Council last week released its submission to the finalising the basin plan ideas consultation process.

NIC chief executive Isaac Jeffrey said one of the recommendations was for the timelines to be extended to allow the states time to complete their SDLAM projects.

“Reports that the minister has asked the MDBA about timelines, signals the minister’s pragmatic approach to finalising the plan and hopefully will lead to agreement around the ministerial council table to extend the timelines,” Mr Jeffrey said.

“Farmers have already given up over 2100GL of water. They’ve done the heavy lifting and it’s time for basin governments to deliver on their commitments, so their failures aren’t sheeted home to farmers and communities.

“If that takes a little more time, then so be it.

“It’s better to have a good plan which works, then a bad plan which destroys jobs, businesses, communities, food availability and the cost of living.”

Digital Editions


  • Golf Notes

    Golf Notes

    MURRAY DOWNS MEN’S Par – Thursday, March 12 Three grades were decided in last Thursday’s Par competition, with Shane Kelly (21) returning the best score…

More News

  • Shop pride on display

    Shop pride on display

    A SURGE of local pride is sweeping through shopfronts across the region, with more than $113,000 set to transform business facades in Swan Hill, Robinvale and Manangatang. Swan Hill Rural…

  • Tougher penalties for ram-raids

    Tougher penalties for ram-raids

    CRIMINALS behind an alleged ram-raid on a Swan Hill tobacco shop in December could be jailed for up to two decades if found guilty. The Victorian Government this week announced…

  • Petition to unmask mural

    Petition to unmask mural

    THE son of a prominent Victorian artist who had an association with Swan Hill is urging locals to support his petition to restore a mosaic mural on the history of…

  • Swans adding to nest

    Swans adding to nest

    The Moulamein Football Netball Club is calling on local teenagers to lace up their football boots, with the club urgently seeking more players to help it field an under 18’s…

  • Author opens page on latest work

    Author opens page on latest work

    ACCLAIMED Australian author Mark Smith will visit Swan Hill later this month to discuss his new psychological thriller, Three Boys Gone. The event will be held at Swan Hill Regional…

  • Smash hit

    Smash hit

    Top level tennis will return to Swan Hill next week, with the ITF ProTour Swan Hill Tennis International getting underway from Sunday at the Ken Harrison Reserve. Among those set…

  • Moulamein funding bid

    Moulamein funding bid

    MOULAMEIN could be set for a major infrastructure boost, with Murray River Council backing a nearly $2 million funding application to revitalise the town’s riverfront and key community assets. At…

  • Royal Commission push back

    Royal Commission push back

    A FIERY clash in Federal Parliament has reignited the bitter fight over the future of the Murray-Darling Basin, with the federal environment minister rejecting claims the government is “destroying family…

  • Duck hunting season opens

    Duck hunting season opens

    THE Victorian duck hunting season began this week with a small number of wetlands closed to shooters, but the decision has reignited the long-running battle between hunters and animal welfare…

  • State of disrepair

    State of disrepair

    RESIDENTS and local leaders are calling for the State Government to urgently address “dangerous” and ongoing defects on the Murray Valley Highway between Swan Hill and Kerang. Lake Charm resident…